Building a deck in Toronto means dealing with the city’s permit system, and honestly, a lot of people get blindsided by what’s actually required. Most deck projects in Toronto need a building permit through the city’s Express web application portal, with fees starting at $206.53. You’ll also have to provide detailed construction plans and site surveys.
We’ve helped plenty of clients through Toronto’s deck permit process, and while it can feel like a headache at first, knowing the main requirements up front can save you hassle, money, and time. The city doesn’t mess around with deck construction—it’s about safety and following the building code, so permits aren’t just bureaucracy. They’re there to protect your investment and your family’s well-being.
This guide covers everything from figuring out if you even need a permit to getting that final inspection signed off. Whether you’re dreaming of a simple attached deck or something more elaborate, knowing how Toronto’s permit process works will help you dodge delays and keep your project on track.
Key Takeaways
- Most deck construction in Toronto needs a building permit through the city’s online Express portal for $206.53
- Permit applications must include detailed construction drawings, site plans, and documentation that match Ontario Building Code standards
- The process involves plan review, construction inspections, and final approval to check for safety and code compliance
When You Need a Deck Permit in Toronto
Most deck projects in Toronto need a permit, but the details depend on your deck’s size, height, and whether it’s attached to your home. Detached structures under certain sizes might be exempt, but renovations to existing decks usually need new permits, too.
Deck Size and Height Regulations
Toronto asks for a deck building permit for most elevated structures, no matter the size. If your deck is more than 600mm (24 inches) above ground, you’ll need a permit.
Ground-level decks still need permits if they’re attached to your house. The city treats these as structural changes that impact your home’s foundation.
Deck area restrictions depend on your neighbourhood and zoning. Most residential properties let you build decks up to 35% of your rear yard area without jumping through extra hoops.
Here’s what usually means you need a permit:
- Decks over 600mm high
- Any deck attached to your house
- Decks with electrical work
- Structures with roofs or enclosures
- Decks that get too close to property lines
People are often surprised that even small attached decks need permits. The city sees these as home additions, not just backyard features.
Detached versus Attached Decks
Attached decks always need permits in the GTA. They’re connected to your house and affect its structure.
Detached decks have a bit more wiggle room. If they’re small and low to the ground, you might not need a permit—if you stick to the rules.
Detached deck exemptions usually mean:
- Height: Under 600mm above ground
- Size: Less than 10 square metres
- Location: Outside setback areas
- Features: No electrical, plumbing, or roof
Attach anything to your house and you’re back in permit territory. Best to double-check with Toronto Building before assuming you’re in the clear.
A lot of folks think “detached” equals “no permit,” but there are still limits. It’s smarter to get answers upfront than deal with compliance trouble later.
Renovations That Require a Permit
Replacing an existing deck? You’ll need a new permit, even if the old one was approved. The current building code always takes priority.
Structural changes trigger permit requirements, too. If you’re changing the size, adding a roof, or messing with the supports, you’ll need approval.
Renovation permits are needed for:
- Expanding or extending your deck
- Adding stairs or railings
- Installing electrical systems
- Structural repairs that affect load-bearing parts
- Turning an open deck into a covered one
Plenty of people assume their old permit covers renovations—not so. Toronto Building doesn’t see it that way.
Minor repairs like staining, swapping out a few boards, or tightening railings don’t need permits. But if you’re replacing big sections or major supports, you do.
You’ll need the same documentation for renovations as for new builds, including updated drawings and code compliance.
Key Building Code and Zoning Requirements
Decks in Toronto have to meet the Ontario Building Code and local zoning bylaws. These rules cover structure, property setbacks, and lot coverage, all of which shape your deck’s design and location.
Ontario Building Code Compliance
The Ontario Building Code lays out the rules for all deck construction in the GTA. We’ve watched projects stall because folks didn’t know these rules ahead of time.
Structural requirements include footing depth, beam spans, and joist spacing. Footings must go below the frost line—usually 1.2 metres deep in Toronto.
If your deck is over 600mm high, you’ll need guard rails at least 1,070mm tall, with specific baluster spacing.
Stair rules matter, too. Riser heights must be 125-200mm, and treads at least 280mm deep.
Decks need to support 1.9 kPa for residential use, which affects everything from joist size to foundation.
The code also wants proper drainage and ventilation under raised decks. We always make sure there’s enough space between boards and a slight slope away from the house.
Toronto Zoning Bylaws
Toronto’s zoning bylaws pile on more requirements. These change by neighbourhood and can really affect your plans.
Permitted deck areas depend on your zoning. Most residential zones allow decks, but there are size limits.
Height restrictions often keep decks below certain elevations. Some neighbourhoods limit high decks to protect privacy and the look of the area.
Coverage rules count deck area toward your total lot coverage. On small city lots, every square metre matters.
Zoning also considers noise and privacy. Some rules require screening or set decks back from property lines to keep things neighbourly.
We always check your zoning before finalizing any design. What works on one block might get rejected on the next.
Setbacks and Lot Coverage Rules
Setbacks decide how close your deck can get to property lines and neighbouring buildings. These rules protect your investment and your neighbours.
Minimum setbacks are usually 0.6–1.2 metres from side and rear lines. Front yard setbacks are stricter.
Corner lots can be tricky—two front yard setbacks can eat into your deck space. We sometimes get creative to make the most of the area.
Lot coverage includes your deck in the total allowed coverage. Most residential zones allow 35–40% coverage for the house and all structures.
Raised decks may get counted differently than ground-level ones. Sometimes the area underneath a raised deck counts, sometimes it doesn’t, depending on height and enclosure.
Some properties have easements or rights-of-way that limit where you can build. We always check the latest survey before moving forward.
Deck Permit Drawings and Documentation
Solid deck permit drawings are the backbone of your Toronto permit application. You’ll need detailed construction plans, accurate site drawings, and paperwork from qualified professionals to get the city’s OK.
Required Plans and Details
Your deck permit drawings have to show construction details that prove you’re meeting code. The city wants footing details—size, spacing, depth, and frost protection.
You’ll need to document all structural elements: column sizes and locations, beam dimensions and spans, and how everything connects.
Stair details are a must if you’re adding stairs. Your drawings should show:
- Tread height and depth
- Headroom above stairs
- Handrail specs and mounting
For guards, the city wants to see opening sizes, climbability, and where guards sit compared to stairs and deck edges.
All drawings need to be on standard-sized sheets, to scale, with every dimension marked. Don’t forget signatures and dates.
Site Plans and Elevations
Site plans set your deck in context. You’ll need a current survey or accurate site plan showing property lines, easements, and rights-of-way.
The plan must show both existing and proposed structures, with exact dimensions. Setback measurements to property lines and buildings are required for zoning checks.
Zoning info should be on the plan:
- Lot area
- Building coverage as a percentage
- Grade elevations for height
- Gross floor area impact
Include parking, driveways, and landscaping. List other structures like sheds, garages, and old decks on the plan too.
Who Can Prepare Your Drawings
Professional engineers can prep your deck drawings and seal them. If you go this route, include the Assumption of Responsibility for Engineering Content Form.
Qualified designers under Ontario Building Code Division C, Part 3, Section 3.2 can also do the job. Their docs need their name, registration number, qualification ID, signature, and a responsibility statement.
We often work with qualified designers who know Toronto’s quirks. They help keep costs down compared to full engineering, and still meet code.
Submit all final drawings and forms as PDFs through Toronto’s online Express portal.
Step-by-Step Deck Permit Application Process
Toronto’s deck permit process has three main steps: put together your documents, pay the fees, and wait for city approval. Here’s how we usually guide clients through it.
Preparing and Submitting Your Application
The City of Toronto now has an online Express portal—way easier than the old paper shuffle. We always recommend it since it spells out exactly what you need and lets you track your application.
You’ll need two main types of documents. First, detailed construction plans: footing specs, beam sizes, stair and guard details. Second, a full site plan: property lines, setbacks, and zoning info.
All drawings should be:
- On standard sheets
- To scale and fully dimensioned
- Signed and dated
- In PDF format
If you’re using an engineer or designer, include their seal and the Assumption of Responsibility form. Missing this stuff is a top reason for delays.
The portal will walk you through what’s needed for your project, so you don’t miss anything important.
Typical Permit Fees
As of January 1, 2025, the standard fee for residential deck permits in Toronto is $206.53. This covers decks, porches, and carports under the residential category.
It’s a pretty straightforward fee structure. You pay up front when you submit through the portal.
Just remember, this only covers the permit. If you need extra approvals from other departments or conservation authorities, those might cost more. We factor these into our estimates when needed.
Timeline for Approval
Permit processing times depend on your project’s complexity and how busy Toronto Building is. Simple decks get through faster than multi-level or complicated designs.
The online portal lets you track your status in real time. That helps us keep clients in the loop about timelines.
We always tell people to apply well before they want to start building. Weather and city delays can mess with your schedule, so submitting early gives you some breathing room.
Inspections, Compliance, and Closing Your Permit
Getting your deck permit is just the start—inspections make sure your build is safe and up to code. You’ll go through several inspection stages, and you need to stay on top of compliance throughout.
Required Stages for Inspection
Most deck permits require a few inspections during construction. Usually, you’ll go through three main ones.
First is the foundation inspection, before you start framing. Inspectors check that footings, posts, and supports meet code.
Next is the framing inspection—once the structure is up but before you lay down decking boards. They’ll look at joist spacing, beam connections, and overall strength.
The final inspection comes after everything’s finished. This covers railings, stairs, the deck surface, and any electrical work.
You’ll need to schedule each inspection through the city’s system or by calling 416-397-5330. Don’t move to the next phase until you pass—otherwise, you might have to redo finished work.
If your deck is extra complex, you might need more inspections for things like built-in seating, roofs, or gas lines.
Post-Approval Responsibilities
Once you start building, it’s on you to keep everything compliant. Keep your approved plans on-site—inspectors will check them.
Stick to your submitted drawings. If you make changes, you’ll probably need to amend your permit, which means more fees and possible delays.
Book inspections as soon as each phase is ready. Waiting too long can slow down your whole project, especially during busy times.
Closing your deck permit is a must when you’re done. Leaving it open can cause headaches if you ever sell your home, since buyers and lawyers want proof everything was inspected.
After your final inspection passes, contact Toronto Building to close your permit. You’ll get confirmation that your project meets all requirements and you’re officially done.
Dealing With Deficiencies
Failed inspections are more common than most folks expect, but honestly, they’re not catastrophic. Inspectors hand you a list of deficiencies to fix before they’ll come back for another look.
Some of the usual culprits: railing heights that miss the mark, weak post connections, or joist spacing that’s off. If you spot these early, you can usually sort them out without too much pain.
Fix everything the inspector notes before you ask for another inspection. Partial fixes just don’t cut it—inspectors want to see that you’ve addressed every issue they listed.
If you can, snap photos of your repairs. It’s not mandatory, but it helps during re-inspection and shows you took the feedback seriously.
Depending on what needs fixing, you might have to pay a re-inspection fee. It’s smart to budget for this possibility when you’re planning out your deck timeline and costs.
Essential Deck Construction Standards
Toronto’s deck construction rules follow the Ontario Building Code plus local bylaws. At the core: solid footings, code-compliant railings, and approved materials.
Footings and Foundation Depth
Deck footings need to go below the frost line or you risk shifting and damage when the ground freezes and thaws. In Toronto, we dig at least 1.2 metres (4 feet) deep.
The Ontario Building Code spells out minimum footing sizes based on how much weight your deck will carry. For most homes, that’s at least 600mm x 600mm (24″ x 24″) at the base.
Footing spacing depends on your beam spans and joist layout, but for a typical deck, we don’t go more than 2.4 metres (8 feet) between footings.
We use galvanized hardware or concrete anchors for post-to-footing connections, making sure they’re rated for the loads. Good drainage around footings is a must—water pooling leads to frost heaving, and nobody wants that.
Railing and Guardrail Code
If your deck surface sits more than 600mm (24 inches) above the ground, you need guardrails. The railing height should land between 1070mm and 1220mm (42″ to 48″) from the deck surface.
Spacing matters:
- Balusters can’t have openings bigger than 100mm (4 inches)
- The gap under the bottom rail can’t go over 100mm
- Avoid horizontal elements that kids might climb
Railings have to handle a horizontal load of 0.75 kN/m (about 50 pounds per linear foot) at the top. We stick to structural-grade lumber or engineered systems that meet these requirements.
Stair railings are a bit different—they need to be between 865mm and 965mm (34″ to 38″) tall, measured from the stair nosing.
Material Requirements
You have to use pressure-treated lumber for all structural parts of the deck that touch or sit close to the ground. We always go with lumber graded Construction Grade or better for joists and beams.
For fasteners:
- Only galvanized or stainless steel screws and bolts
- No plain nails for anything structural
- Joist hangers must be galvanized and sized right for your lumber
If you’re thinking about composite decking, it needs to meet CSA standards for load-bearing. We always double-check that alternative materials have engineering approval before using them.
Where the deck attaches to your house, flashing and moisture barriers are non-negotiable. We install proper ledger board flashing to keep water out and avoid rot.
Frequently Asked Questions
Getting a deck permit in Toronto means submitting specific paperwork, paying a $206.53 fee, and following both the Ontario Building Code and local bylaws. Not every deck needs a permit—approval depends on the deck’s size, location, and foundation.
What are the specific requirements for obtaining a deck permit in Toronto?
You’ll need detailed construction drawings—footings, beams, columns, stairs, guard rails, all of it. Everything should be on standard sheets, drawn to scale, and fully dimensioned.
The site plan has to show property lines, setbacks, existing and new buildings, and zoning info. You’ll also need to mark parking, driveways, and any other structures on your lot.
If an engineer seals your drawings, add an Assumption of Responsibility for Engineering Content Form.
Submit all documents as PDFs, along with the Application for a Permit to Construct or Demolish. As of January 2025, the permit fee is $206.53.
Can you walk me through the process of applying for a deck building permit with the City of Toronto?
You can apply online now through Toronto Building’s Express web portal. It’s a lot smoother than it used to be. The system tells you exactly what documents you need and flags any outside approvals.
You can track your application from start to finish—no more guessing if your paperwork disappeared into a black hole.
Prepare all your drawings and documents first, then upload them to the portal. The system checks for completeness before moving it along.
Does every deck project in Toronto need a permit, or are there exceptions based on size or type?
Not all decks need a permit in Toronto. Smaller, low decks that don’t raise structural or safety concerns might be exempt.
The exact size and height limits can shift depending on municipal rules.
It’s always best to check with Toronto Building before you assume you’re exempt. Better safe than sorry—especially if you plan to sell your house or deal with insurance later.
How does the Ontario Building Code impact deck construction in Toronto?
The Ontario Building Code lays out all the rules for decks in Toronto—structure, safety, and how you build it. Toronto Building reviews every permit to make sure you’re following the Code.
You have to follow minimum railing heights, maximum gaps between balusters, stair tread sizes, and load requirements. These aren’t suggestions—they’re the law.
The Code also covers footing depth, beam spans, and connection specs. We usually design decks to beat these minimums for extra safety and longevity.
I’m planning a backyard reno; will pouring concrete for my deck’s foundation require a separate permit?
Concrete footings for decks are usually included in your deck permit. Just make sure your original drawings show all the footing details—size, spacing, depth, frost protection.
If you’re planning big concrete work, like pads, retaining walls, or major grading, you might need extra permits.
Always bring up the full scope of your concrete plans during your first permit meeting. Toronto Building can tell you if you need anything else for your project.
How can I ensure my deck design meets the City of Toronto’s bylaws and gets approved without a hitch?
First thing’s first: I always check the latest zoning bylaws—setbacks, lot coverage, height limits—since these rules can shift depending on the neighbourhood or even the property itself. It’s easy to miss a detail if you don’t dig into those specifics.
Honestly, teaming up with folks who’ve navigated Toronto’s permit maze before makes life a lot easier. We’ve seen the usual headaches that get permits rejected, so we tweak the design early on to sidestep those traps.
I make it a habit to run through the city’s checklist and match every drawing to what they want. If I skip a detail, it just means more emails and wasted time. Getting it right the first time really speeds things up.